CLIENT: MISSISSIPPI DEPARTMENT OF TRANSPORTATION
WORK COMPLETION: TBD
TOTAL CONSTRUCTION COST: UNKNOWN

TEI was selected by the Mississippi Department of Transportation (MDOT) to provide the following professional services:

Redesign the intersection with U.S. 49 to remove the skew and flying "Y" configuration
• Conduct a topographic and boundary survey for the project (U.S. Highway 49 Corridor and Mississippi Highway 42 Corridor)
• Develop three alternatives for the realignment of the Mississippi Highway 42 intersection with U.S. Highway 49
• Prepare and submit conceptual plans for the project to include roadway plans
• Investigate all local roads within the project limits to determine if realignments are necessary
• Fully-actuated traffic signal will be constructed 

Prepare and submit the following:

• Conceptual, preliminary, field review/office review, and final plans