2016
CANAL ROAD RE-ROUTE
CLIENT: MISSISSIPPI POWER COMPANY
Tice Engineering was selected by Mississippi Power Company to perform a topographic survey and prepare acquisition documents for approximately 6 miles of transmission line right-of-way.
The new route was established to accommodate the new MS State Highway 601 interchange with Interstate 10.
SCOPE OF WORK INCLUDED:
Full topographic survey of right of way
Drafting all features
Producing a PLS-CADD file for design purposes
Preparation of acquisition documents to purchase right of way across 21 parcels