2014
KEMPER COUNTY EROSION CONTROL DESIGN AND INSPECTION SERVICES
CLIENT: MISSISSIPPI POWER COMPANY

Tice Engineering was selected to conduct Erosion Control Inspections and direct contractors on installation procedures for Best Management Practices (BPM) to minimize stormwater runoff. Approximately 148 miles of new transmission lines, CO2 lines, water lines, and gas lines were constructed.

On a weekly basis, TEI monitored the rights-of-way, documented the deficiencies, and wrote reports to keep the project in compliance with the MDEQ permit.

SCOPE OF WORK INCLUDED:
Monitoring of the rights-of-way to document deficiencies
Weekly reporting to keep the project in compliance with the MDEQ permit
Coordination of contractors on-site repairing deficiencies to erosion control measures

Previous
Previous

Canal Road Re-route